Building 73.5 invites our community to help design the future of our schools—creating safe, innovative spaces where every child can thrive.

Below, you can view the presentation from our recent Community Engagement event, where our consulting team shared and explained the results of the district-wide facilities survey, along with the accompanying slide deck.

Dear Skokie 73.5 Families, 

At a recent Board of Education meeting, the decision was made to delay our Building 73.5 community engagement program. There are three major reasons. 

First, our district is facing a significant financial challenge — a $3.5 million shortfall. Balancing our budget, while maintaining a great quality of education for our kids, is our highest priority. 

A second factor is property tax collections by Cook County. While this is complicated, the bottom line is that collections are down, payments to our district are delayed, yet property taxes for many of our homeowners are up. 

Third, at a December Building 73.5 meeting, a large majority preferred a "land swap" option — building a new John Middleton School on the park to the west of the school and then developing a park on the school’s existing site. But survey results, and discussions over the holidays, indicated that this land swap idea is not possible. So we must go back to the drawing board. 

So, reluctantly, the decision was made to postpone our community engagement program, balance the budget, then turn our direction to the start the new school.  Our focus must be on cost-effectively providing our kids with the best education possible. 

For those who worked on our community engagement program, including our leadership “Engagement Team” group, please accept my humble thanks for your time, wisdom and input. It was hugely appreciated. Please know that this is just a pause — we will get back to facility planning. The issue is too important to ignore.

Please call or email if you have questions. It is my honor and privilege to serve as your superintendent of schools. I don’t take that responsibility lightly. I know that I work for you. 

Dr. Charles Kyle
Superintendent


VIEW VIDEO PRESENTATION FROM CES 4
CLICK OR TAP THE SLIDE BELOW TO VIEW THE FULL SLIDE DECK

Tax impact

TIMELINE

FALL 2024: Architectural Facility Assessment

SPRING 2025: Building 73.5 Community Input: Educational Needs, Building Needs

  • Community Engagement Session 1
  • Community Engagement Session 2

SUMMER 2025: Architects Develop Options

FALL 2025: Building 73.5 Community Input, Options and Costs

  • Community Engagement Session 3

WINTER 2025

  • Community Engagement Session 4

SPRING 2026

  • Anticipated Open Houses (early spring)
  • Anticipated Community Engagement Session 5

LATE SPRING 2026

  • Building 73.5 Final Report presented to Board of Education
THANK YOU!

Options Presented at December 11, 2025, Community Engagement Session

MAINTENANCE PLAN ONLY

QUICK FACTS

  • 10-Year Completion
  • $45 Million Estimated Total
  • Taxpayer Increase: $298 Annually for 20 Years

FACT SHEET 

MAINTENANCE + ALTERNATE SITE

QUICK FACTS

  • 10-Year Completion for McCracken and Meyer Maintenance Plan
  • 3-Year Completion for Replacement of Middleton
  • $105 Million Estimated Total
  • Taxpayer Increase: $1,284 Annually for 30 Years on $400K Home

FACT SHEET 

Approval from Village and Park District Required on Replacement Options

The option below, originally introduced as "OPTION 2" at CES 3, is no longer under consideration as of CES 4:

PHASED REPLACEMENT OF MIDDLETON + 10-YEAR MAINTENANCE PLAN

QUICK FACTS

  • 10-Year Completion for McCracken and Meyer Maintenance Plan
  • 6-Year Completion for Phased Replacement of Middleton
  • $131 Million Estimated Total
  • Taxpayer Increase: $1,616 Annually for 30 Years on $400K Home

FACT SHEET 

Approval from Village and Park District Required on Replacement Options